• Projects In Motion

    Welcome to our facilities updates page, where we'll provide news, images, videos and more on these vital campus projects.

    We will keep our community apprised of additons to this page, but please do check back for ongoing news on our additions and renovations as we strive to meet our goal completing construction by the start of the 2020-21 school year!

    ConstructionPictures

What's Happening NOW

  • Progress:

    • PLE
      • Concrete - Formed and placed first area of footings
      • Site Utility - Storm water piping to the courtyard was complete
      • Excavation - Foundation excavation continued
    • Horizon
      • Concrete - Completed grade preparation for the slab on grade
      • Precast - Cut in new windows and doors in the gym precast walls
      • Plumbing - Interior roof drain piping began
    • Asa Clark
      • Utilites - Storm piping for the 6th grade addition started

    "Next Wave" Goals (2 Weeks):

    • Site
      • Earthwork - Finish grade the practice soccer field
    • PLE
      • Concrete - Complete foundation work
      • Masonry - Start masonry walls
      • Demolition - Start demolition at the existing third grade wing
    • Horizon
      • Roofing - Contractor to start roofing activities
      • Concrete - Complete concrete slab on grade
      • Mechanical and Electrical - Begin above ceiling rough-ins
    • Asa
      • Site Utility - Complete storm water and water main relocation for the 6th grade addition

Weekly Construction Updates